Supply Signal
Your Chip Supplier Is Asking for More Wafers.
By Supply Signal | November 11, 2026 | 6 min read

This week, the everyday parts got busy.
The clearest supply facts for a buyer this week came from three makers of ordinary parts, not from the AI-optics or foundry news. Microchip calls itself a broadline supplier. Diodes sells analog and power parts. onsemi sells power and sensing technologies.
Microchip says lead times are lengthening across its supply chain. Diodes says its new capacity is coming online into busier factories. onsemi says rising power needs are speeding up demand in its AI data center and industrial end markets.
That is a reason to confirm the lead time, the order coverage and the stock status of the ordinary chip, analog and power lines on your 2027 builds now, before the lengthening reaches your quotes. Do not chase only the scarce AI parts.
Microchip Says Lead Times Are Lengthening
If Microchip parts are on your 2027 builds, get a current quoted lead time for each part number, from your distributor and from Microchip, and record each answer with its date.
"Lead times are lengthening across our supply chain," says chief executive Steve Sanghi. He says Microchip is working to expand capacity and secure additional wafer allocation. He gives no figure in weeks and names no product line.
The statement covers Microchip's whole supply chain.
Sanghi says bookings remained robust, with book-to-bill well above one, consistent with recent quarters. September-quarter net sales were $1.622 billion, up 42.2% from a year earlier and 9.2% from the prior quarter, above the high end of Microchip's guidance.
I read a book-to-bill well above one, quarter after quarter, as orders that arrive faster than Microchip ships them. A lead time quoted before this quarter may no longer hold.
Microchip also expects a firmer December quarter than its normal season. It guides net sales between down 3% and up 1% from the prior quarter, with a midpoint of down 1%. Its normal December-quarter pattern is down 3% to 5%. Microchip says that, once about $53 million of infrequent September-quarter revenue items are taken into account, the midpoint is 5% to 7% better than normal seasonality.
Capacity moves more slowly. Microchip says it paused most of its factory expansion and reduced its planned capital investment through fiscal 2027, while it adds equipment to selectively expand production capacity. I read the push for more wafer allocation as Microchip looking for wafers to meet its orders, without a large new factory build behind it.
For single-source Microchip lines, replace rolling forecasts with firm forecasts or scheduled orders that cover at least the next two quarters.
Diodes Is Loading the Capacity It Added
If Diodes analog and power parts are on your 2027 builds, confirm the quoted lead time and the validity period of each open quote, part number by part number.
Diodes says the targeted investments it made in capacity expansion over the past year are now coming online. Chief executive Gary Yu says the resulting increase in loading at its factories lifted gross margin, along with product mix and pricing improvements. That is Diodes' explanation of its own margin, and I make no price forecast from it.
Demand is moving through its channel as well. Diodes reported record third-quarter revenue of $532.6 million, up 35.8% from a year earlier and 19.5% from the prior quarter. Global point-of-sale (POS), which I read as sales out of its distribution channel, was also a record, up more than 30% from a year earlier.
Yu says the sequential growth came mainly from record automotive revenue, stronger demand across broad industrial applications, and AI ecosystem applications that brought record revenue in computing. Diodes expects fourth-quarter revenue of about $550 million, plus or minus 3%.
I read the higher loading as new capacity being put to use. Diodes does not say which product lines are tight, and it names the risk that it may not keep its current factory loadings, so I make no lead-time claim for Diodes.
onsemi Says Power Needs Are Speeding Up Demand
If onsemi power parts are on your 2027 builds, confirm lead time and allocation for each part number before you release orders, and ask in writing whether any of them is scheduled for a fab move or a product change notice.
"Increasing power requirements are driving accelerated demand," chief executive Hassane El-Khoury says of onsemi's AI data center and industrial end markets. AI data center revenue grew 39% from the prior quarter and 175% from a year earlier.
The growth is uneven across onsemi. The segment it reports as PSG had $889.9 million of third-quarter revenue, up 21% from a year earlier, while its AMG and ISG segments each grew 2% from a year earlier.
The growth is concentrated in one segment, and the chief executive ties the faster demand to power. Ask about each part, and do not assume one answer for the whole company.
onsemi is also working on its plants. Chief financial officer Thad Trent points to "our ongoing fab right initiatives." I read that as onsemi reshaping its factory footprint. The release does not say which parts are affected, and it gives no lead-time or allocation figure.
What to Watch For
I am watching these conditions for you.
- Microchip's lead times. Whether Microchip puts a figure in weeks on the lengthening, or names the product lines it affects. Today it gives neither.
- Microchip's order book. Whether book-to-bill stays well above one in the December quarter, and whether net sales land inside its guidance range of $1.573 billion to $1.638 billion.
- Microchip's capacity. Whether Microchip restarts the factory expansion it paused, raises the capital plan it reduced through fiscal 2027, or reports that it has secured more wafer allocation.
- Diodes' loading. Whether fourth-quarter revenue lands near its $550 million outlook, whether POS stays at a record, and whether Diodes names any product line as tight.
- onsemi's demand and plants. Whether AI data center revenue keeps growing from quarter to quarter, and whether onsemi names the parts affected by its fab right initiatives.
What To Do This Week
- Re-quote every Microchip part number on your 2027 builds, with your distributor and with Microchip, and record each answer with its date. Do not call a build clear-to-build on a lead time quoted before this quarter.
- Place firm forecasts or scheduled orders that cover at least the next two quarters for single-source Microchip lines, in place of rolling forecasts.
- Ask your distributor, for each Microchip, Diodes and onsemi part, whether it ships from stock on hand or waits for factory output.
- Confirm the quoted lead time and the validity period of each open Diodes quote, part number by part number.
- Escalate one written question to onsemi or your distributor: are any of your parts scheduled for a fab move or a product change notice? If yes, get the last-time-buy date and the requalification plan in writing now.
- Qualify a pin-compatible second source for single-source lines where your engineers approve the fit.
- Model 2027 total cost of ownership with a buffer-stock line for each critical part that ships only against factory output.
Microchip wants more wafers while its orders run ahead of its shipments. Diodes is loading the capacity it added over the past year. onsemi's demand is speeding up in its AI data center and industrial end markets, where power needs are rising.
These are the everyday lines on a 2027 build, beside the scarce AI parts that already get a buyer's attention. A lengthening lead time shows up in the quote before it shows up in a headline.
The everyday parts are getting busy. Confirm them while their quotes are still current.
Sources: Microchip Technology second-quarter fiscal 2027 results; Diodes Incorporated third-quarter 2026 results; onsemi third-quarter 2026 results. Company outlooks are their own expectations, and Microchip lists its lead-time and wafer-allocation statements among its forward-looking statements. The readings of book-to-bill, POS and factory footprint are my own.